update wazo keyring before 2021-11-27

Description

Currently the wazo keyring will expired 2021-11-27
To avoid crisis/panic, we must take action before this date (e.g. renew the key)

We should probably generate a new key instead of just bumping the expiration date.

We should probably also use a master key to generate subkeys.

Activity

Show:
Clément Bourgeois
January 4, 2021, 2:00 PM

Should be at in review, following advise

François Blackburn
December 24, 2020, 4:16 PM
Edited

Do you know if we have a procedure about these steps? Maybe it should be interesting to add it to the wiki

I block the ticket until a response, but all it’s merged and functional

Sébastien Duthil
December 23, 2020, 10:42 PM

Done:

  • update expiration for mirror key and builder key

  • update mirror key in GPG directories on mirror

  • update mirror key in http://mirror.wazo.community/wazo_current.key

  • PR in wazo-keyring

  • update builder key in jenkins and rebuild docker image for builder

Sébastien Duthil
February 6, 2020, 6:34 PM

Here’s a discussion on debian-derivatives regarding this problem:

https://lists.debian.org/debian-derivatives/2019/05/msg00003.html

Done

Assignee

Sébastien Duthil

Reporter

François Blackburn

Sprint

None

Labels

Approvers

François Blackburn

Pair

None

Fix versions

Priority

High